No. | WORK DESCRIPTION /PROJECT | CLIENT | CONTRACT PERIOD | DATE COMPLETION |
---|---|---|---|---|
1. | Propose design, build, testing commissioning and maintainance of Putra Height interchange and toll plaza at KM 13.2 North South link expressway for sime uep Heights Sdn. Bhd. | PKNS INFRA BERHAD | 15.03.07 | 09.01.09 |
2. | Kerja-kerja menaiktaraf Tiga(3) Jalan Ladang di Wilayah III, Mada. | DAMAI SETIA SDN. BHD. | 10.12.08 | 30.04.09 |
3. | Cadangan pembinaan jambatan dari simpang panchor pengkalan Datu, Mukim Panchor, Daerah Kemumin, Kota Bahru, Kelantan. | DAMAI SETIA SDN. BHD. | 17.02.09 | 31.10.09 |
4. | Construction of roadworks, roadside drain, water reticulation and sewer reticulation (package 4) at proposed intergrated township development of Bandar Bukit Raja (stage 1), Mukim Kapar, Daerah Klang, Selangor Darul Ehsan. | PKNS INFRA BERHAD | 24.09.08 to 23.12.09 | 23.11.2009 |
5. | Proposed Design and Build of a New Pumping Station and Reticulation Works Including Related Works for the Subang Jaya City Centre (SJCC) Development at Subang Jaya for Sime UEP Centre Sdn Bhd | SIME UEP CENTRE SDN BHD | 08.04.10 | 15.09.2010 |
6. | Proposed Construction and Completion of Infrastructure Works and TNB Substation At Zone 6A Development Of Nilai impian & Nilai Utama, Mukim Setul, Daerah Seremban, Negeri Sembilan darul Khusus | NEGARA PROPERTIES REALTY SDN BHD | 24.02.10 to 01.12.10 | 28.11.2010 |
7. | Proposed PavementRehabilitation And Associated Wprks At KM 32.0 – KM 29.7 Southbound, Along Malaysia – Singapura Second Crossing, Section S5 | PLUS | 14.06.10 to 04.11.10 | 01.11.2010 |
8. | Senai – Pasir Gudang – Desaru Expressway Package 3C/6 (480mm ALTERNATIVE DESIGN PAVEMENT) | RANHILL ENGINEERS AND CONSTRUCTOR SDN BHD | 09.06.09 to 31.01.11 | 31.01.2011 |
9. | The execution and completion of Mosque for the Asian Institute of Medicine Science and Technology University Mukim Semeling, Daerah Kuala Muda,Kedah Darul Aman. | MIED CAPITAL SDN BHD | 10.03.10 to 12.01.12 | 30.03.2012 |
10. | Cadang Membina Jalan Keluar Masuk Di KM 18.5 Lebuhraya Persekutuan (Arah Kuala Lumpur)Bandar Glenmarie Daerah Petaling Untuk Bisraya. Sdn Bhd Shell Trading Malaysia Sdn Bhd Dan Bonus Saujana Sdn Bhd | MOHD ASBI & ASSOCIATES | 05.07.10 to 03.01.11 | 27.03.2012 |
11. | Cadangan ,Merekabentuk, Membina dan Menyiapkan 1422 Unit Rumah Berkembar Satu Tingkat dan Kerja-kerja Infrastruktur Yang Berkaitan untuk Penempatan Semula Setinggan Bukit Botak (Taman Selayang Mutiara) Bandar Baru Selayang, Mukim Batu, Daerah Gombak, Kuala Selangor, Selangor Darul Ehsan | PKNS INFRA BERHAD | 11.08.10 to 10.05.12 | 16.07.2012 |
12. | Proposed Bukit Gambir Interchange and Toll Plaza (Phase 1 – Advanced Earthworks) | PLUS | 12.08.10 to 10.08.11 | 20.01.2012 |
13. | Proposed Sungai Buaya Interchange and Toll Plaza | PLUS | 14.06.11 to 13.06.13 | 15.10.2013 |
14. | The construction and Completion of Main Infrastructure Works and 6 nos TNB Sub Station | SIME DARBY ELIMINA DEVELOPMENT SDN BHD | 29.08.2013 to 02.05.2015 | 12.06.2015 |
15. | Proposed Construction and completion of Main Drain on Part of Lot and Part of PT 32127, Daerah Seremban, Negeri Sembilan for Proposed Mixed Development Resident and Commercial for Bandar Ainsdale,Mukim Rasah, Seremban. | SIME DARBY AINSDALE DEVELOPMENT SDN BHD | 29.08.2013 to 02.05.2015 | 06.08.2015 |
16. | Menaiktaraf Jalan Muar-Tangkak-Segamat, Johor ( Fasa 1: Segamat – Tangkak ) Pakej 1B | JKR | 01.11.2011 | 30.7.2015 |
17. | Proposed Reparation of the Existing Main Road & Drainage at PH 11 and PH 14, Laying of Main Road Pavement Final Layers at PH 11, PH 14 and Eastern Division and Installation of Safety Railing at Main Roads PH 11 and PH 14 for Handing Over to MPK for Proposed Integrated Township Development of Bandar Bukit Raja (Stage 1) on Lots 19,25,27, 52, 1635, 13046 and 13047 , Mukim Kapar, Daerah Klang, Selangor Darul Ehsan. | SIME DARBY USJ DEVELOPMENT SDN BHD | 07.01.2016 | 24.05.2016 |